Re-ordering Parent/Child assets within a Schedule

Top  Previous  Next

Re-ordering a Parent or Child asset within a schedule will NOT cause associated assets to be moved at the same time.  To keep parent and child assets together in the same sequence within a schedule, they should be selected and moved in one operation.

 

1.Highlight the appropriate Schedule from the Site List screen and select "Schedule Schedule For" from the Side Bar.
2.Ensure the Indicator Column is available:
Select Utilities > Configure > Schedule Settings from the resultant menus.
Click the "Display Indicator Column" option.  A tick indicates that the option is enabled.

       (NOTE: Once enabled, this setting will be retained by Prime for future use).

3.Toggle Edit Mode to ON.
4.Select the parent and child assets by highlighting the first asset, holding down the Shift key and clicking on the last required asset.  (NOTE: Dots in the Indicator Column identify those assets selected).
5.Drag the assets to their new location and drop them in place.
6.Click the Save icon to save the changes.