| 1. | Navigate to the schedule which contains the asset and its sub-assets. |
| 2. | Toggle Edit Mode to ON. |
| 3. | Click on the sub-asset(s) which are to be parented: |

| 4. | Right-click, and select " Re-parent" from the subsequent menu. |
| 5. | The "Re-parent Assets" dialog box will open: |

| 6. | Highlight the intended Parent asset to select it: |

| 8. | The child item will now display directly under the new parent asset and appears slightly indented and in grey type: |

| 9. | Click the icon to save the changes. |
|